2013 Street Maintenance (Micro Surfacing) Schedule
 
Posted on Thursday May 23, 2013
 
The City will be looking at micro surfacing along 6th Street from Eisenhower to Franklin June 5th and June 6th.
 

Kaw Valley Enginnering and the City of Junction City would like to inform property/business owners of the City's Street Maintenance Program for the work along 6th Street in the coming weeks.  The City will be looking at micro surfacing along 6th Street from Eisenhower to Franklin, while maintaining traffic.

 

The schedule will be as follows:

 

June 5th - Eisenhower to Jackson will be completed

June 6th - Jackson to Franklin will be completed

 
 